C.J. Parker Construction Limited (in liq) v Ketan – [2017] NZCA 3 – Winkelmann, Brewer and Toogood JJ – 3 February 2017

Motel renovations – no contract, agreed price or terms as to payment method and claims – reasonable value of work under s17(4) Construction Contracts Act 2002 – whether invoice was valid “payment claim” under s20 – whether payers’ response valid “payment schedule”